Timelines for planning permissions
Timescale for most planning permission cases:
Stage | Timescale | Action |
Public notices |
| Notice published in newspaper and site notice erected. |
Receipt of application | Two weeks | Application must be lodged within two weeks of publication of newspaper notice. |
Submissions/observations | Five weeks | Submissions/observations can be submitted within the first five weeks of receipt of application. |
Notice of decision | Eight weeks | Planning authority issue notice of their decision on the application within eight weeks of receipt of application. (Alternatively, they may request further information.) |
Appeal | Four weeks | A decision may be appealed to An Bord Pleanala within 28 days of a decision. |
Final grant | Four weeks | If the decision is not appealed to An Bord Pleanala, then the planning authority will issue a final grant of permission. |